How quickly can you get a WMS for your webshop?

Picture of Posted by Bill Denbigh

Posted by Bill Denbigh

June 15, 2022

When choosing a WMS for your webshop, make sure you have a clear understanding of the supplier’s implementation process before signing a contract. Implementation is arguably the most challenging – and riskiest – phase of a WMS project. Everyone in the industry has either heard or can share a WMS implementation story that was delayed or massively over budget… and sometimes both.

The good news is that Tecsys has a webshop WMS designed to go from initial scoping interview to live in 28 days. When customers hear that timeframe, we’re always asked, “How is that possible?”

Let me walk you through the steps and processes Tecsys uses to implement WMS in 28 days.

Implementation plan for webshop WMS

At Tecsys, we divide the implementation into four phases. Each phase is seven working days and has a checkpoint at the end to ensure the project is on track. The phase must be completed successfully before moving on to the next phase.

Phase 1: Understand your business and project scope

At the start of an implementation project, it is very important for Tecsys to learn about your business and, in collaboration with you, to define how the system will support your inventory management. Below are the steps we go through in phase one:

  • Tecsys vil gennemgå din nuværende drift og se, hvordan I driver jeres lager, og hvordan I visualiserer jeres ultimative løsning.
  • For at give kontekst og noget indledende læring vil Tecsys præsentere en end-to-end webshop WMS-løsning og gennemgå hver af kernekomponenterne i lagerstyringsløsningen. Vi vil også vise et implementeringsprojektoverblik, så du forstår, hvordan systemet ser ud, og hvordan Tecsys kommer til at køre implementeringen.
  • Når alle i teamet forstår, hvordan implementeringen vil køre, vil Tecsys tildele roller og ansvar for hvert trin i implementeringsprojektet.
  • Mod slutningen af ​​de syv hverdage vil Tecsys udføre en detaljeret proceskortlægning og systemkonfigurationsgennemgang. Dette er det punkt, hvor vi gennemgår hver proces på lageret, der vil blive udført, og sikrer, at hver enkelt er klart forstået og giver mening. Eventuelle specifikke konfigurationer eller processer er dokumenteret.

Phase one is marked as completed when both parties have agreed on a SOP (Standard Operating Procedures) for the warehouse and an implementation plan with tentative dates and names assigned to each task.

Phase 2: Build system data, configuration and interfaces

Using all the information we collected in phase one, Tecsys builds your webshop WMS while you or your system integrator builds the ERP/webshop integration. Here are the steps to phase two:

  • Cloudløsningen er implementeret, og Tecsys bygger stamdatatabeller, varer, produktkatalog, lagerzoner, lokationer osv. Vi opretter også en indledende indlæsning af data i WMS.
  • Tecsys bygger også den centrale konfiguration af WMS’et til jeres webshop ved hjælp af SOP dokumentet defineret i fase et.
  • Når jeres systemintegrator eller it-team har bygget standardgrænsefladerne, kører Tecsys en test af grænsefladetest og en datavalidering.
  • Med masterdatatabellerne, kernekonfigurationen og grænsefladerne på plads, kan Tecsys køre den første end-to-end systemtest. På nuværende tidspunkt behandler vi alle kernelagertransaktioner og sikrer, at datacyklusserne er effektive i hele systemet, og at alle processer fungerer korrekt.

Phase two is marked as completed when both parties have agreed that all data are correctly carried over and the master tables are correctly loaded.

Phase 3: Test the system and processes, train key staff

Now the webshop WMSs are built and the data is in place. The next step is to test and train key warehouse staff as super users. Below are the steps in phase three:

  • Tecsys gennemfører en pilot af jeres nye WMS med alle nøgletransaktioner på lageret for at sikre, at alt fungerer som planlagt, og der ikke er problemer med data eller processer.
  • Nøglemedarbejderne involveres, og Tecsys sikrer at de kan køre lagerstyringen uden problemer.
  • Under trænings- og valideringsprocessen udfører Tecsys også end-to-end systemtest for de indlæste processer og data.
  • Mod slutningen af ​​fase tre færdiggøres detaljerne i go-live planlægning. Begge parter er enige om, hvornår og hvordan go-live sker, hvem der skal køre hvilke aspekter af go-live, og hvilke nøgleelementer, der er nødvendige for en vellykket go-live.

Phase three is marked as completed when both parties approve the go-live plan.

Phase 4: Roll-out and training of remaining staff

The webshop WMS go-live is the final phase of the implementation plan. Below are the steps involved in phase four:

All warehouse workers are trained by the internal super users and live simulated transactions are tested in the system. When everyone is ready, the system resets and is ready to go live.

The whole team performs a stock count. After completion, the system is put into live mode.

Tecsys assists key staff with go-live support to ensure the system is live and users are productive and working efficiently with the WMS.

Preparation is the key to success

My best recommendation is that you be prepared before you begin phase one of this implementation plan. All the hard work you do beforehand will really help make the implementation as smooth as possible for your business.

The main advantage of rapid deployment is that it reduces risk and shortens time-to-value. Tecsys has had many successful go-lives for our WMS when following this 28-day implementation plan. Tecsys WMS is designed to quickly get your business up and running on a fully integrated e-commerce inventory management system, so you can reduce your costs and start saving money.